A given project has a BAC = $20,000, AC(cumulative to date) = $12,500, and EV(cumulative to date) = $12,700. Using CPI as a basis for future cost efficiency, what is the ETC? A) $7,000 B) $7,185 C) $7,556 D) $8,000